Transforming Transportation Infrastructure

This 90 km highway project stands as a large-scale initiative to enhance regional connectivity and traffic flow. With seven interchanges, extensive earthworks, and robust bridge construction, the project reflects high standards in road engineering and infrastructure execution. Scheduled over a 48-month contract, it involves the full scope of earth and civil works across a vast terrain.

Project Value

56,521,740.00 USD

Nature of Work

Executing all Earth & Civil works for a 90 km freeway with 7 interchanges.

Contract Duration

48 Months

Project Technical Specifications

ComponentUnitQuantity
Bridge (50m Span)No.10
Small BridgeNo.398
ExcavationM3462,000
Embankment / BackfillM310,702,000
FormworkM2169,600
RebarKg3,359,000
ConcreteM3164,000
Roads: Crushed Rock BaseM31,166,000
Roads: Granular Sub-baseM3588,000
Asphalt BinderM2/cm43,402,000
Asphalt TopekaM2/cm13,354,000